AQW 11317/11-15 Mr Stewart Dickson Alliance Party East Antrim
Tabled Date: 03/05/2012 Answered On Date: 09/05/2012 Priority Written: No
Question: To ask the Minister for Regional Development for an update on Translink’s plans for a new Belfast transport hub.
Answer:
The plans to construct a new Transport Hub in Belfast are still at an early stage. Translink has submitted a Strategic Outline Case which my Department and the Department of Finance and Personnel have approved. Translink is now in the process of developing the Outline Business Case for the project. When complete this will also be submitted to my Department for approval.
|