AQW 29420/11-15


Mr Michael McGimpsey
Ulster Unionist Party
South Belfast


Tabled Date: 12/12/2013
Answered On Date: 19/12/2013
Priority Written: No


Question:
To ask the Minister of Health, Social Services and Public Safety (i) whether the planned opening of the critical care building at the Royal Victoria Hospital has been delayed because of issues arising from the construction contract; (ii) when the building will open; (iii) to detail the cost of any defects with the building or from the contract; and (iv) whether the Health Service will incur costs from the defects and the delayed opening of the business.


Answer:
The planned opening of the critical care building has been delayed by the discovery of pipe-work corrosion problems which necessitated the complete removal and replacement of all five sealed water systems in the building; these were installed under the construction contract and the issue must be resolved under the terms of contract;
It is now planned to bring the building into operation on a phased basis in the latter half of 2014 and early 2015;
The contractor is responsible for the cost of repair and the details of the costs incurred by the contractor are not therefore available; and,
The Trust has had to incur expenditure (e.g. additional design team fees, expert opinion, etc.) which will now have to be recovered from the contractor in the settlement of the case.