AQW 29422/11-15


Mr Michael McGimpsey
Ulster Unionist Party
South Belfast


Tabled Date: 12/12/2013
Answered On Date: 19/12/2013
Priority Written: No


Question:
To ask the Minister of Health, Social Services and Public Safety what was the original planned opening date of the critical care building at the Royal Victoria Hospital.


Answer:
Before discovery of the pipe-work corrosion problems, the building was to be handed over on 12 November 2012 and the Trust intended to bring the building into operation on a phased basis – theatres on 19 March 2013, critical care beds on 10 April 2013, and the emergency department on 18 May 2013. The upper three (maternity) floors were not to come operational until the new Maternity Building is completed in mid 2017.