Question: To ask the Minister of Health, Social Services and Public Safety to outline the next phase of the capital building works on behalf of the Southern Eastern Health and Social Care Trust at the Ulster Hospital.
Answer:
The next phase of the Ulster Hospital Phase B Redevelopment will see construction progress from the current inpatient ward block to the new acute services block. This latest redevelopment programme commenced in June 2013 with construction of a new ward block which is due to be completed in late 2016. Enabling works for the new Acute Services Block have already commenced and construction of the main building is due to start in Autumn 2015. The Acute Services Block will provide a new emergency department, inpatient radiology, assessment unit, specialist wards and support services. The Trust has also plans for its inpatient mental health unit to be located on the Tor Bank site at the Ulster Hospital and is working with the Department to finalise a business case for this proposal. There is no timeframe or plans agreed for the next phase of redevelopment, or for any further significant upgrade or replacement work at the Ulster Hospital site, beyond the completion of the ongoing work on the generic ward and acute services blocks.
|