AQW 38210/11-15


Mr Patsy McGlone
Social Democratic and Labour Party
Mid Ulster


Tabled Date: 04/11/2014
Answered On Date: 10/11/2014
Priority Written: No


Question:
To ask the Minister of Justice what has been the cost to date of developing the joint public services college at Desertcreat.


Answer:
As at 30 September, the total spend on the project was £9.6m. This excludes the £2.85m in relation to site acquisition.
The Department is not undertaking any option studies of alternative sites. Such studies would only be appropriate if the current project was unable to proceed as planned.