AQW 51204/11-16


Mr Stewart Dickson
Alliance Party
East Antrim


Tabled Date: 20/11/2015
Answered On Date: 07/12/2015
Priority Written: No


Question:
To ask the Minister for Regional Development to account for the delays to the Enterprise service on the day of its relaunch; and the unreliability of the rolling stock in general.


Answer:
Translink has advised me that the 11:00 hours Enterprise departure from Dublin Connolly on 16 November 2015 was delayed by 88 minutes due to severe wheel slip in Balbriggan area of the Irish Republic. Low adhesion on the railway line resulted in significant delays and damage to the train wheels.
Over the past six months the performance of the services on the Belfast to Dublin route for punctuality and reliability has been a 99.93% score for reliability and a 93.8% for punctuality. Punctuality is defined as trains arriving at their destination either on time or within 10 minutes as set out in the timetable.
The Passenger Charter targets for the Dublin line are that 99.5% of trains will operate and 90% of trains will arrive no more than 10 minutes late. These targets have been more than achieved.