AQW 3084/16-21


Mrs Rosemary Barton
Ulster Unionist Party
Fermanagh and South Tyrone


Tabled Date: 14/09/2016
Answered On Date: 28/09/2016
Priority Written: No


Question:
To ask the Minister of Education to outline how much of the budget allocated to the Strule Shared Education Campus has been spent to date.


Answer:
The construction forecast spend from the 1 April 2010 up to 31 March 2017 for the Strule Shared Education Campus is £19.3m. This includes the costs associated with for example, the design of the six schools and shared educational facilities, construction of Arvalee School and Resource Centre which opened on 6 September 2016, site enabling and preparation works, statutory charges, professional fees and initial road works. This estimate does not include other non-construction programme costs.