AQW 7064/16-21


Mr Alan Chambers
Ulster Unionist Party
North Down


Tabled Date: 14/11/2016
Answered On Date: 06/12/2016
Priority Written: No


Question:
To ask the Minister of Health (i) when the new ward block at the Ulster Hospital is due to be handed over from the contractor; (ii) when it will be fully operational; and (iii) whether target dates for these events have been met.


Answer:
Handover of the new ward block is imminent. It was scheduled for 14 November 2016 however the contractor has informed the Trust of a delay. A new date has not yet been set.
Following a phased decant of services it is intended that the building will be fully operational by Summer 2017;
As indicated the contractor has informed the Trust of a delay to the handover date. A delay to the facility becoming operational is not expected.