AQW 7064/16-21 Mr Alan Chambers Ulster Unionist Party North Down
Tabled Date: 14/11/2016 Answered On Date: 06/12/2016 Priority Written: No
Question: To ask the Minister of Health (i) when the new ward block at the Ulster Hospital is due to be handed over from the contractor; (ii) when it will be fully operational; and (iii) whether target dates for these events have been met.
Answer:
Handover of the new ward block is imminent. It was scheduled for 14 November 2016 however the contractor has informed the Trust of a delay. A new date has not yet been set. Following a phased decant of services it is intended that the building will be fully operational by Summer 2017; As indicated the contractor has informed the Trust of a delay to the handover date. A delay to the facility becoming operational is not expected.
|