To ask the Minister of Education in relation to the Strule Education Campus in Omagh, to detail the expected (i) start date; and (ii) completion date.


Answer:
The Strule Programme is a pioneering project and a massive capital investment in the delivery of education in the region. It is a longstanding Executive priority.
The Department continues to work closely with the six school principals and their teams to build on the culture of sharing in Omagh through a wide range of shared education initiatives.  These innovative programmes are being developed and led by the schools themselves to ensure today’s students have the opportunity to enjoy the benefits of sharing, and play an important role in shaping future education delivery both locally and regionally.
The next stage of construction has been delayed due to tendering issues. The Department has completed a fundamental review of the construction programme and I will be giving consideration to the issues raised.
In light of this delay the go live date has been revised. Provisional opening of the Campus is planned for September 2024 at the earliest. This is dependent on works commencing on site by May 2021 at the latest.
In the meantime all other work on the Programme, including construction and non-construction projects, is continuing uninterrupted. The site preparation works are substantially complete and Strathroy Link Road was completed in November 2019.