AQW 1848/17-22 Mr Andrew Muir Alliance Party North Down
Tabled Date: 10/02/2020 Answered On Date: 25/02/2020 Priority Written: No
Question: To ask the Minister for Infrastructure for an update on when the North West Transport Hub will be fully completed, including the active and sustainable travel centre.
Answer:
European funding of the project requires the Hub to be fully operational by 31st December 2020. Phase 1 of the project was completed in October 2019 with the opening of the old Waterside Railway Station. The second phase, which will see the opening of the sustainable travel centre, park and ride facilities and bus drop off facilities remains ahead of this schedule with completion due in the summer of this year.
|