To ask the Minister for Infrastructure, pursuant to AQW 5118/17-22, (i) how she will determine if the project is fit for purpose; (ii) what areas may not be fit for purpose currently; and (iii) how these can be remedied.


Answer:
In advance of the next stage of the York Street Interchange scheme, and in line with good practice in relation to the development of major transport projects, I have commissioned a short, sharp external review designed to ensure an approach to the scheme that is future-proofed and forward looking. This will be informed by stakeholders and specialists to ensure that any scheme is fit for purpose.
I am conscious that much of the development work was carried out several years ago and am keen to ensure that the scheme we move to procure is one capable not only of connecting people to opportunities but also of promoting sustainable travel, improving road safety and enhancing the north end of the city centre in a way that can benefit not only those who rely on the road but also those who live and work close to it. Designing and developing our infrastructure means meeting the needs of all of our community and our wider environment now and for future generations.
Terms of Reference for the review are available at: -
https://www.infrastructure-ni.gov.uk/articles/york-street-interchange-overview.