AQW 5857/17-22


Mr Stewart Dickson
Alliance Party
East Antrim


Tabled Date: 27/07/2020
Answered On Date: 10/08/2020
Priority Written: No


Question:
To ask the Minister for Infrastructure whether the dualling of the Dargan Viaduct will be prioritised as part of the future proofing of the York Street Interchange project.


Answer:
As part of the development of the York Street Interchange project, a feasibility study on the dualling of the Dargan Viaduct has been completed. It is proposed that works to strengthen the foundations and piers of the Dargan Viaduct will be delivered as part of the York Street Interchange as future proofing for further work.