AQW 13667/17-22 Mr Andrew Muir Alliance Party North Down
Tabled Date: 28/01/2021 Answered On Date: 04/02/2021 Priority Written: No
Question: To ask the Minister for Infrastructure why her Department is unwilling to consider further measures to reduce and inhibit bridge collisions on Ballysallagh Road, Craigantlet, following collisions in recent times.
Answer:
Following a bridge strike in early 2018 my officials carried out a review which resulted in a series of additional signs being erected. This brings the total number of signs on the bridge and the approach roads to fifteen. Officials have installed significant signage and markings on the approaches and on the bridge to alert drivers to its presence. I am advised this is sufficient and as such there are no plans for further measures at this time. There are limitations to what my Department can do and there is a responsibility on drivers of high vehicles who are expected to know their vehicle size and to plan their routes to avoid hazards such as low bridges.
|