AQW 16320/17-22


Mr Andrew Muir
Alliance Party
North Down


Tabled Date: 12/03/2021
Answered On Date: 19/03/2021
Priority Written: No


Question:
To ask the Minister of Education for an update on the progress of the Crawfordsburn Primary School new build construction project.


Answer:
The major capital investment project to provide suitable accommodation for an 8 class base primary school for Crawfordsburn Primary School is progressing well.
The Integrated Consultancy Team (Design Team), Isherwood & Ellis LLP, appointed in October 2019, is currently finalising the RIBA Stage 3 (Developed Design) which is due for submission to my Department’s technical advisors in April 2021.