AQW 17120/17-22 Ms Paula Bradshaw Alliance Party South Belfast
Tabled Date: 12/04/2021 Answered On Date: 23/04/2021 Priority Written: No
Question: To ask the Minister for Infrastructure what risk assessments have been carried out on the planned toucan crossing at Durham Street, Belfast.
Answer:
All the proposed road and pedestrian crossings that are planned to be installed as part of the Belfast Transport Hub project on Durham Street have been subject to an independent Road Safety Audit which was carried out on the scheme in May 2017. As the scheme progresses, the detailed design for the crossings will be carried out in accordance with current design standards and engagement/consultation between Translink and DfI Roads.
|