AQW 17432/17-22 Mr Andrew Muir Alliance Party North Down
Tabled Date: 15/04/2021 Answered On Date: 23/04/2021 Priority Written: No
Question: To ask the Minister for Infrastructure to detail (i) the cycle routes delivered under road improvement and resurfacing schemes by Roads Eastern Division in each of the last five years; and (ii) a summary of the number of schemes and length broken down by facility type as defined in departmental guidance "Measures to regulate traffic RSPPG E063" (a) totally separate facility; (b) cycle lane on the carriageway; and (c) share walking/cycling facility.
Answer:
Details of the cycling facilities that have been constructed by my Department within Roads Eastern Division in the previous 5 years, by facility type, are provided in the following table: Year | Scheme Name | Type of cycling facility provided | Length (KM) | 2020-21 | Blaris Greenway Phase 3 | Greenway | 1.4km | | Dublin Road | Pop Up | 0.63km | | Grosvenor Road | Pop Up | 0.55km | | Crumlin Road | Pop Up | 1.0km | | Donegall Road | Pop Up | 0.80km | | A55 Knock Road / Glen Rd | Crossing | - | 2019-20 | Broadway | Shared | 0.12km | | Blaris Greenway Phase 1 / 2 | Greenway | 1.4km | 2018-19 | Middlepath Street | Two-way | 0.37km | | Middlepath Street | Shared | 0.15km | | Middlepath Street | Two-way | 0.29km | | Comber Greenway (Comber Rd /Old Dundonald Greenway included) | Greenway | 2.4km | | Laurelhill Road | Shared | 1.2km | 2017-18 | Castledillon | Shared | 0.05km | | Comber Greenway | Greenway | 4.8km | 2016-17 | College Sq North | Two-way | 0.19km | | College Sq North | Shared | 0.06km | | Durham St | Two-way & Shared | 0.15km | | Durham St | Shared | 0.07km | | College Ave to Castle Street | Contraflow | 0.13km | | | Total length (KM) | 15.76km |
|