AQW 17518/17-22 Mr Andrew Muir Alliance Party North Down
Tabled Date: 16/04/2021 Answered On Date: 04/05/2021 Priority Written: No
Question: To ask the Minister for Infrastructure to detail how much has been spent on the York Street Interchange Project, in each of the last ten years.
Answer:
The following table provides a breakdown of the annual spend to date on the York Street Interchange in each of the last ten years. Financial Year | £k | 2011/12 | 602 | 2012/13 | 877 | 2013/14 | 850 | 2014/15 | 1,523 | 2015/16 | 3,250 | 2016-17 | 1,073 | 2017-18 | 4,936 | 2018-19 | 2,380 | 2019-20 | 1,639 | 2020-21 | 2,344 | Total | 19,474 |
|