AQW 22176/17-22


Ms Kellie Armstrong
Alliance Party
Strangford


Tabled Date: 10/09/2021
Answered On Date: 27/09/2021
Priority Written: No


Question:
To ask the Minister of Agriculture, Environment and Rural Affairs to confirm how many weeks the Northern Ireland Environment Agency has taken to provide a statutory consultee response to planning applications for (i) 2019; (ii) 2020 and (iii) 2021 to date, broken down by council area.


Answer:
Most responses made by the Department to planning application consultations are a single collated response covering all relevant Departmental divisions rather than individual responses from each division. As such response rates are reported at a Departmental level.
The table below provides the average number of weeks the Agency has taken to provide a statutory consultee response to planning applications for the reporting periods: 1 April 2018 to 31 March 2019; 1 April 2019 to 31 March 2020 and 1 April 2020 to 31 March 2021 broken down by Council area.
The response rate for 1 April 2021 to 31 August 2021 has also been provided.
Council
2018/19
Average Number of Weeks
2019/20
Average Number of Weeks
2020/21
Average Number of Weeks
01/04/2021-31/08/2021
Average Number of Weeks
Causeway Coast & Glens
2.5
3.6
3.7
1.6
Mid & East Antrim
3.6
5.6
5.5
2.4
Antrim & Newtownabbey
3.3
4.0
5.8
2.1
Belfast
2.2
2.9
5.4
2.1
Lisburn & Castlereagh
1.8
2.2
2.9
1.1
Ards & North Down
2.6
3.6
3.8
1.7
Newry, Mourne & Down
3.6
3.5
5.7
2.0
Armagh, Banbridge, Craigavon
3.3
3.3
4.6
1.9
Mid Ulster
4.3
5.0
6.0
2.3
Fermanagh & Omagh
4.5
5.8
7.2
1.9
Derry & Strabane
3.7
4.8
6.1
2.2