AQO 2386/17-22 Mr Cathal Boylan Sinn Féin Newry and Armagh
Tabled Date: 06/09/2021 Answered On Date: 13/09/2021 Priority Written: No
Question: To ask the Minister of Justice for an update on the redevelopment of Magilligan Prison, including whether the outline business case has been submitted.
Answer:
The OBC 1 for the Redevelopment of Magilligan is currently being finalised, and it is expected to be submitted to DoF later this month. Progress on redeveloping the Magilligan site has however been made, with the majority of the work to upgrade the incoming power supply due to be completed by the end of March 2022, costing in the region of £4.3 million.
|