AQW 27312/17-22 Mr John Blair Alliance Party South Antrim
Tabled Date: 13/12/2021 Answered On Date: 02/02/2022 Priority Written: No
Question: To ask the Minister of Education to provide a timeframe in which the outstanding task orders at Crumlin Integrated College will be completed.
Answer:
It will take some time to establish an up to date position regarding the outstanding task orders at Crumlin Integrated College. My Estate Operations Team will forward this to you as soon as it is received from the Education Authority (EA). In relation to minor works, the EA has advised that: the ventilation scheme to partially upgrade windows has been approved and is expected to complete by March 2022; a partial roofing scheme is also being considered for delivery in the 2022/23 financial year subject to competing priorities and available funding; and a feasibility study is being progressed for potential traffic management works.
|