AQW 29365/17-22 Mr John Blair Alliance Party South Antrim
Tabled Date: 07/02/2022 Answered On Date: 14/02/2022 Priority Written: No
Question: To ask the Minister for Infrastructure, pursuant to AQW 27597/17-22, when resurfacing of the Largy Road in Crumlin will commence.
Answer:
Phase 1 of the resurfacing scheme on Largy Road, Crumlin, running between Crumlin Road and House No.42B, commenced on 18 January 2022 and is due to be completed by the end of February 2022. My officials have advised it is their intention to complete Phase 2, from House No.42B to the end, as part of the 2022/23 work programme, subject to the availability of funding.
|