To ask the Minister of Education to detail the (i) original estimated cost; and (ii) current estimated cost of completing the Strule Shared Education Campus, Omagh.


Answer:
The estimated total cost of completing the Strule Shared Education Campus in 2016 was £169m. The current estimated cost is £232m which includes the costs of construction, including a contingency for construction price inflation, risk and optimism bias; staffing the Programme; and other running costs, including support being provided to the schools for shared curricular development and implementation. It should be noted that the 2016 figure did not include an allowance for inflation.
Costs will continue to be kept under review.