AQW 774/22-27 Ms Paula Bradshaw Alliance Party South Belfast
Tabled Date: 30/05/2022 Answered On Date: 08/06/2022 Priority Written: No
Question: To ask the Minister for Infrastructure for an update on the provision of a pedestrian and cycle bridge from the Gasworks to Ormeau Embankment, Belfast.
Answer:
The statutory processes for this project have been completed and, following its inclusion in the Belfast Region City Deal, my officials have commenced preparations for the procurement phase. It is estimated that it will take approximately 3.5 years to complete the procurement, detailed design and construction phases.
|