AQW 1906/22-27 Mr Andrew Muir Alliance Party North Down
Tabled Date: 21/06/2022 Answered On Date: 29/06/2022 Priority Written: No
Question: To ask the Minister for Infrastructure to detail how many scheduled roads resurfacing projects in North Down, which were included in his Department's 2021/22 Annual Report, have not been completed due to the legal challenge of the asphalt resurfacing contract competition.
Answer:
Five schemes in the planned programme for 2021/22 were not completed prior to the expiry of the asphalt resurfacing contract in November 2021 at: Hawthorne Drive, Bangor; Beechwood Avenue, Bangor; Beechwood Gardens, Bangor; Silverstream Drive, Bangor; and Kinnegar Drive, Holywood. Should you have any further questions on this matter, please contact DfI Roads Southern Division at: dfiroads.southern@infrastructure-ni.gov.uk.
|