AQW 2883/22-27


Ms Connie Egan
Alliance Party
North Down


Tabled Date: 06/09/2022
Answered On Date: 16/09/2022
Priority Written: No


Question:
To ask the Minister for Communities to detail plans for new build social housing in North Down for the next five years.


Answer:
The Social Housing Development Programme (SHDP) is currently formulated on a 3-year basis. The information below is therefore provided on that basis.
In the North Down Parliamentary Constituency there are currently 30 social housing units under construction. I have provided the details of these in Table 1 below.
A further 163 social housing units are programmed to start as part of the SHDP 2022/23 – 2024/25. I have provided the detail of these units is provided in Table 2 below.
Please note that programmed schemes can be lost or slip to future programme years for a variety of reasons e.g. relating to delays in acquiring sites and/or failure to secure Planning Approval. Additional schemes can also be added to the SHDP ‘in-year’ through Competitive Land, Design & Build procurement route and/or the purchase of Existing Satisfactory / Off-the-Shelf properties.
The programme formulation process for the SHDP 2023/24 – 2025/26 is currently underway, and further schemes may be added in the North Down Parliamentary Constituency in due course, subject to Departmental/Ministerial Approval.
Table 1: Social housing units under construction in the North Down Parliamentary Constituency
Housing Association
Scheme Name
Location
Type
Units
Onsite Year
CompletionYear
Clanmil
Savoy Redevelopment (Blocks B & C)
Bangor
New Build
26
2021/22
2023/24
North Belfast HA
21 Copeland Avenue
Millisle
Rehab
1
2020/21
2022/23
North Belfast HA
3 Lisnabreen Terrace
Bangor
Rehab
1
2021/22
2022/23
North Belfast HA
32 Lisnabreen Crescent
Bangor
Rehab
1
2021/22
2022/23
North Belfast HA
5 Ballyhalbert Gardens
Bangor
Rehab
1
2021/22
2022/23
Table 2: Social housing units programmed to start through the SHDP 2022/23 – 2024/25 in the North Down Parliamentary Constituency
Housing Association
Scheme Name
Location
Type
Units
Onsite Year
CompletionYear
Ark
Donaghadee Road
Bangor
New Build
8
2022/23
2023/24
Habinteg
Balmoral Dale
Bangor
Off-the-Shelf
5
2022/23
2023/24
North Belfast HA
53 Lisnabreen Crescent
Bangor
Rehab
1
2022/23
2022/23
North Belfast HA
79 Skipperstone Road
Bangor
Rehab
1
2022/23
2022/23
North Belfast HA
10 Abbey Gardens
Millisle
Rehab
1
2022/23
2022/23
Clanmil
Bangor Marina Regeneration
Bangor
New Build
32
2023/24
2025/26
Habinteg
Balmoral Dale, Phase 2
Bangor
New Build
12
2023/24
2024/25
Radius
Castle Street
Comber
New Build
14
2023/24
2024/25
Radius
Cannyreagh Road
Donaghadee
New Build
15
2023/24
2024/25
Choice
Worcester Avenue
Bangor
New Build
74
2024/25
2027/28