AQW 4223/22-27 Mr Andrew Muir Alliance Party North Down
Tabled Date: 06/10/2022 Answered On Date: 21/10/2022 Priority Written: No
Question: To ask the Minister for Infrastructure to outline the planned spend during the current and future financial years on the York Street Interchange Scheme.
Answer:
In the absence of an Executive, budgets have not been agreed for the 2022-23 financial year or future years. However, to ensure that my Department continues to develop and deliver much needed investment in our infrastructure, I agreed capital allocations for 2022-23 which include £1.4m for the on-going development of the York Street Interchange project. Future funding will be dependent on Executive priorities and associated budget settlements.
|