To ask the Minister of Education to detail the (i) timeline; and (ii) budget to complete the Strule Shared Education Campus.


Answer:
The previous Main Works procurement competition has been closed and the Department formally commenced a fresh Main Works procurement competition with the release of the Invitation to Tender on 13 December 2021.
On the current programme timetable, subject to all necessary approvals being in place, contract award is planned for spring 2023. Assuming successful appointment of a main works contractor and following the pre-construction design period, construction is due to begin on site autumn 2023 and is currently planned to complete in 2026, with campus opening planned for September 2026.
The estimated budget required to complete the Campus is £183m. This includes the costs of construction, including a contingency for construction price inflation, risk and optimism bias; staffing the Programme; and other running costs, including support being provided to the schools for shared curricular development and implementation.
Costs will continue to be kept under review.