AQW 6058/22-27 Mr Eóin Tennyson Alliance Party Upper Bann
Tabled Date: 09/02/2024 Answered On Date: 21/02/2024 Priority Written: No
Question: To ask the Minister for Infrastructure for an updated timeline for the reinstatement of the Moylinn East Footbridge, Craigavon.
Answer:
The Department remains committed to taking forward the replacement of Moylinn East Footbridge which will be subject to the completion of a business case, the need to secure funding, and statutory processes such as planning permission. It is hoped that planning will be in place within the next 6 months, to allow the project to be procured, subject to available funding.
|