AQW 6318/22-27


Ms Connie Egan
Alliance Party
North Down


Tabled Date: 13/02/2024
Answered On Date: 29/02/2024
Priority Written: No


Question:
To ask the Minister for Infrastructure for an update on the works to address the recurrent flooding on Bridge Road, Helen’s Bay.


Answer:
Following extensive investigation works at Bridge Road, Helen’s Bay, officials have determined that the recent flooding was attributed to damaged drainage within private property. A temporary solution was installed in December 2023 which has been successful in preventing a reoccurrence of flooding during recent prolonged periods of rain. My Department is currently taking forward a design of a new drainage system to substantively resolve the matter and it is hoped this will be delivered in the 2024/25 financial year.