Question:
To ask the Minister of Health for an update on progress at the proposed Fort George health hub.


Answer:
The Outline Business Case for the Fort George Health Hub was approved by the Department of Health on 15 March 2021. The Western Health & Social Care Trust (WHSCT) appointed an Integrated Consultancy Team to design the new Hub on 24 November 2021.
WHSCT have been working with the Department for Communities as the design of the new Health Hub has progressed to review the impact of the inclusion of the Health Hub on the wider masterplan for the Fort George site.
A submission for a “Pre-Application Discussion” (PAD) with the Planning Authority regarding the application for the Health Hub and its impact on the wider site masterplan was lodged by DfC on 28 September 2022. WHSCT purchased the portion of the site required to build the Health Hub from DfC in March 2023.
The design of the Health Hub has progressed, and is ready to be submitted for Planning Approval. Discussions with statutory authorities through the PAD process regarding the wider masterplan and the Health Hub remain ongoing.