To ask the Minister for Communities to detail (i) the current budget estimate for completion of the Casement Park project; (ii) his assessment on the basis of value for money of the project; and (iii) the status of the business case.


Answer:
The current budget allocation for the Casement Park Project, approved by the Executive in 2011, is £62.5 million. The GAA have committed a contribution of £15 million and the Irish Government has announced its intention to contribute over £40 million. Any additional funding requirements will have to be agreed with partners. For commercial reasons, I cannot comment further on costs at this time.
The assessment of value for money for the project will form part of the business case process.
Work is progressing on completion of an updated Business Case.