To ask the Minister for Infrastructure for an update on the progress of the Portadown Flood Alleviation Scheme.


Answer:
The Portadown Flood Alleviation scheme is currently at the detailed design stage and work is ongoing to complete the design and finalise the business case.
This work includes refining aspects of the proposed defences following completion of tree surveys and consultation on an addendum to the Environmental Statement for the scheme.
Consultation on the Environmental Statement Addendum will commence in April.
Subject to gaining the necessary approvals and the availability of funding, it is currently estimated that the procurement process to appoint a contractor for the works could commence in Autumn 2024.