AQW 10784/22-27 Ms Paula Bradshaw Alliance Party South Belfast
Tabled Date: 24/04/2024 Answered On Date: 08/05/2024 Priority Written: No
Question: To ask the Minister of Education what steps he is taking to ensure work is progressed urgently on the roof replacement at Cairnshill Primary School.
Answer:
An architect led design team has been appointed for the roof replacement works at Cairnshill Primary School. It is currently anticipated that design will be completed mid-May, with construction to commence in June.
|