AQW 11623/22-27


Ms Kellie Armstrong
Alliance Party
Strangford


Tabled Date: 09/05/2024
Answered On Date: 15/05/2024
Priority Written: No


Question:
To ask the Minister of Education for an update on (i) the build progress; and (ii) an expected date of completion for each integrated school being supported through Fresh Start capital monies.


Answer:
The following table summarises the status and actual or expected completion dates for projects funded through Fresh Start. Please note this includes shared education campuses as well as integrated schools.
School
Status
Completion
Drumlins IPS
Completed
September 2017
Braidside IPS
Completed
July 2020
Enniskillen IPS
Completed
January 2023
Limavady SEC
Completed
August 2023
Roe Valley IPS
Completed
December 2023
Mill Strand IPS
In construction
Summer 2024
Phoenix IPS
In construction
Summer 2024
Parkhall IC
In construction
Autumn 2024
Ulidia IC
In construction
End 2024
Shimna IC
In construction
Summer 2025
Rowandale IPS
In construction
Autumn 2025
New Bridge IC
In construction
End 2025
Strangford IC
In construction
Autumn 2026
Ballycastle SEC
In construction
Summer 2027