AQW 12221/22-27 Mr Stewart Dickson Alliance Party East Antrim
Tabled Date: 20/05/2024 Answered On Date: 29/05/2024 Priority Written: No
Question: To ask the Minister of Education to detail (i) the schools in East Antrim awaiting the completion of capital projects; (ii) the progress, status, and anticipated completion dates of these projects; and (iii) the current prioritisation ranking of these projects.
Answer:
There are currently seven capital projects in East Antrim awaiting completion. The current position of these projects is as follows: School | Current Position | Islandmagee Primary School | Project is in the construction stage, with completion anticipated in summer 2024. | St Killian’s College | Project is in the design stage and a revised planning application is to be submitted in the coming months. | Belfast High School | The project was announced in March 2022, however was paused in April 2023. | Carrickfergus Academy | Procurement of an Integrated Consultant Team for the project has commenced, following the re-start of the project in February 2024. | Larne Grammar School | The project was announced in March 2022, however was paused in April 2023. | Larne High School | The project was announced in March 2022, however was paused in April 2023. | Ulidia Integrated College | Project is in the construction stage with completion anticipated by the end of 2024. |
Projects will continue to advance in planning and design but will only be permitted to progress to construction when affordable within the wider education budget context. As I have previously stated, it is my intention to continue to make the case for significant additional and sustained capital budget to invest right across the schools’ estate.
|