AQW 12850/22-27 Mr Brian Kingston Democratic Unionist Party North Belfast
Tabled Date: 03/06/2024 Answered On Date: 11/06/2024 Priority Written: Yes
Question: To ask the Minister for Infrastructure when the procurement exercise for the Crumlin Road Gaol Visitor and Conference Centre is (i) commencing; and (ii) concluding.
Answer:
The procurement for the new Operator for the Gaol Visitor Attraction and Conference Centre is being taken forward by Construction and Procurement Delivery CPD and commenced in February 2024 with a Pre-Market Engagement exercise. The work is ongoing, and it is expected to be complete later this year
|