AQW 13012/22-27


Ms Liz Kimmins
Sinn Féin
Newry and Armagh


Tabled Date: 05/06/2024
Answered On Date: 12/06/2024
Priority Written: Yes


Question:
To ask the Minister of Health for an update on the (i) planning application; (ii) delivery timeline; and (iii) funding secured for the new children’s hospital.


Answer:
The New Children’s Hospital and demolition of Bostock House planning application was submitted on 21st August 2018 and approved on 18th April 2019. This approval is not subject to expiry as the approved works have commenced.
The New Children’s Hospital is projected to commence on site in early 2025 subject to Full Business Case approval in summer 2024. The building works are programmed for a period of 4.5 years to complete in summer 2029. A commissioning phase will follow with the hospital expected to be operational by Q4 2029/30.
As the New Children’s Hospital is an Executive flagship project, it will be prioritised and funded from the Department’s capital budget through to completion.
Whilst it is not possible to identify and secure revenue funding so far in advance of the completion of the project, it is expected that revenue funding to support the running and additional staffing of the New Childrens Hospital will be prioritised from future budget settlements.