AQW 14010/22-27 Mrs Diane Dodds Democratic Unionist Party Upper Bann
Tabled Date: 01/07/2024 Answered On Date: 15/08/2024 Priority Written: No
Question: To ask the Minister of Health for breakdown of the annual spend to date on the Mother and Children's Flagship hospital.
Answer:
To date, £184.0m has been spent on the Maternity and Children’s Flagship project. This has delivered the new Maternity building (Phase B1) and associated enabling works packages at c.£92.0m, the office and logistics building known as ‘Non-Clinical Support’ at c.£15.3m, Bostock House Demolition at c.£6.75m, and a series of demolitions and site clearance enabling contracts, ducts and complex services diversions including c.£8.1m duct, c. £2.2m Site Wide Infrastructure, c.£2.3m Spine Road Duct Crossing, c.£5.5m Energy Centre enabling works, c.£1.5m temporary decants, c.£6.3m West Access Road, on which the overall Maternity and Children's Flagship project is interdependent. The c.£44.05m balance of expenditure to date includes professional design works, equipment costs, statutory fees, management and tendering processes. Full Business Case approval for the new Children’s Hospital was received on 5 July 2024. The design phase is complete, with the main construction phase due to start on site in early 2025 and scheduled to run for a period of 4.5 years until summer 2029. A commissioning phase will follow, with the hospital expected to be operational by Q4 2029/30. A breakdown of the annual spend to date on the Maternity and Children’s Flagship project, including the above enabling projects, is provided in the table below. Year | Spend (£) | 2011-12 | 30,000 | 2012-13 | 1,832,000 | 2013-14 | 4,381,100 | 2014-15 | 4,999,192 | 2015-16 | 5,695,514 | 2016-17 | 5,955,828 | 2017-18 | 17,086,845 | 2018-19 | 31,258,366 | 2019-20 | 36,045,695 | 2020-21 | 21,607,709 | 2021-22 | 28,429,329 | 2022-23 | 16,088,085 | 2023-24 | 10,527,907 | 2024-25 | 99,336 | Total to date | 184,036,906 |
|