AQW 14010/22-27


Mrs Diane Dodds
Democratic Unionist Party
Upper Bann


Tabled Date: 01/07/2024
Answered On Date: 15/08/2024
Priority Written: No


Question:
To ask the Minister of Health for breakdown of the annual spend to date on the Mother and Children's Flagship hospital.


Answer:
To date, £184.0m has been spent on the Maternity and Children’s Flagship project. This has delivered the new Maternity building (Phase B1) and associated enabling works packages at c.£92.0m, the office and logistics building known as ‘Non-Clinical Support’ at c.£15.3m, Bostock House Demolition at c.£6.75m, and a series of demolitions and site clearance enabling contracts, ducts and complex services diversions including c.£8.1m duct, c. £2.2m Site Wide Infrastructure, c.£2.3m Spine Road Duct Crossing, c.£5.5m Energy Centre enabling works, c.£1.5m temporary decants, c.£6.3m West Access Road, on which the overall Maternity and Children's Flagship project is interdependent. The c.£44.05m balance of expenditure to date includes professional design works, equipment costs, statutory fees, management and tendering processes.
Full Business Case approval for the new Children’s Hospital was received on 5 July 2024. The design phase is complete, with the main construction phase due to start on site in early 2025 and scheduled to run for a period of 4.5 years until summer 2029. A commissioning phase will follow, with the hospital expected to be operational by Q4 2029/30.
A breakdown of the annual spend to date on the Maternity and Children’s Flagship project, including the above enabling projects, is provided in the table below.
Year
Spend (£)
2011-12
30,000
2012-13
1,832,000
2013-14
4,381,100
2014-15
4,999,192
2015-16
5,695,514
2016-17
5,955,828
2017-18
17,086,845
2018-19
31,258,366
2019-20
36,045,695
2020-21
21,607,709
2021-22
28,429,329
2022-23
16,088,085
2023-24
10,527,907
2024-25
99,336
Total to date
184,036,906