To ask the Minister of Health to detail the timeframe for the Mother and Children's Flagship hospital being fully operational.


Answer:
The Maternity and Children’s Flagship project will provide a new Regional Children’s Hospital which will deliver integrated and contemporary paediatric healthcare services and a new Maternity Hospital which will provide modern facilities for enhanced maternity and obstetric services. The project also includes associated site and energy infrastructure.
The Maternity Hospital main building (Phase B1) reached construction completion in March 2024 and was handed over to the Belfast Trust to commence the clinical commissioning phase, with a target operational date of November 2024. Unfortunately, testing of the water systems showed the presence of pseudomonas contamination which makes it unsafe to transfer clinical services to the new building until remedied. The Belfast Trust is now working to identify potential remediation options: however, this is likely to result in a delay in opening the hospital until it is clinically safe to do so.
The remaining phases B2 and B3 of this project (demolition of part of the existing maternity building to accommodate the link bridge between the new maternity and critical care building) to facilitate the relocation of inpatient and outpatient maternity services from the existing maternity building to Floors 7-9 of the Critical Care Building, will be delayed until the new Maternity Hospital has opened, as the new building will provide the space required to decant services to enable these works to take place.
The New Children’s Hospital is projected to commence on site at the beginning of 2025 following Full Business Case approval received in July 2024. The building works are programmed for a period of 4.5 years to complete in summer 2029. A commissioning phase will follow with the hospital expected to be operational by Q4 2029/30.