AQW 15116/22-27


Mr Daniel McCrossan
Social Democratic and Labour Party
West Tyrone


Tabled Date: 16/09/2024
Answered On Date: 30/09/2024
Priority Written: No


Question:
To ask the Minister for Communities for an update on the funding of Casement Park.


Answer:
The current budget allocation for the Casement Park project, approved by the Executive in 2011, is £62.5 million. The UCGAA contribution remains at £15 million, while the Irish government announced in January 2024 its intention to contribute €50 million (circa £43 million).