AQW 17933/22-27


Mr Gerry Carroll
People Before Profit Alliance
West Belfast


Tabled Date: 11/11/2024
Answered On Date: 26/11/2024
Priority Written: No


Question:
To ask the Minister for Infrastructure (i) whether construction of Grand Central Station is over-budget; and (ii) for a breakdown of costs incurred to date.


Answer:
The full business case for the Belfast Transport Hub was approved in 2021 at a total cost of £294.6m. The expenditure to date is £280.4m and the revised estimated project cost is £344.5m. The majority of this cost increase is due to the extraordinary inflation that has impacted on all major capital projects. The costs incurred to date are as follows.
Element
Letter of Offer Budget
Professional and management Fees
£11,382,115
Statutory Fess & Surveys
£310,960
Land
£710,732
Enabling Works
£2,799,855
Main works
£142,140,731
Railway Signalling & Telecommunications
£68,878,203
Preparatory Ground Works
£53,260,000
Road works
£948,431
TOTAL
£280,431,027
A revised Final Business Case is currently being considered by my Department.