AQW 17933/22-27 Mr Gerry Carroll People Before Profit Alliance West Belfast
Tabled Date: 11/11/2024 Answered On Date: 26/11/2024 Priority Written: No
Question: To ask the Minister for Infrastructure (i) whether construction of Grand Central Station is over-budget; and (ii) for a breakdown of costs incurred to date.
Answer:
The full business case for the Belfast Transport Hub was approved in 2021 at a total cost of £294.6m. The expenditure to date is £280.4m and the revised estimated project cost is £344.5m. The majority of this cost increase is due to the extraordinary inflation that has impacted on all major capital projects. The costs incurred to date are as follows. Element | Letter of Offer Budget | Professional and management Fees | £11,382,115 | Statutory Fess & Surveys | £310,960 | Land | £710,732 | Enabling Works | £2,799,855 | Main works | £142,140,731 | Railway Signalling & Telecommunications | £68,878,203 | Preparatory Ground Works | £53,260,000 | Road works | £948,431 | TOTAL | £280,431,027 |
A revised Final Business Case is currently being considered by my Department.
|