AQW 20463/22-27 Ms Sian Mulholland Alliance Party North Antrim
Tabled Date: 13/01/2025 Answered On Date: 29/01/2025 Priority Written: No
Question: To ask the Minister for Infrastructure for an update on the start date of the construction works on Glenshesk Road, Ballycastle, following two landslides.
Answer:
The B15 Glenshesk Road partially collapsed due to an embankment failure on 27 March 2024. The design process is nearing completion and when a final design is established, a construction programme will be developed and taken forward. It is anticipated that a construction start date in spring of this year is achievable. In relation to the second slippage associated with Storm Bert, I can advise that the Glenshesk Road has been fully open at this location (Ballycastle side of Greenan Road), since 11 December 2024. My Department has provided a dedicated webpage to keep interested parties advised of progress on the Glenshesk Road reopening. This can be viewed at https://www.infrastructure-ni.gov.uk/articles/b15-glenshesk-road-ballycastle-overview
|