To ask the Minister for Infrastructure to detail when the improvement works at Cairnshill park and ride facility will (i) begin; and (ii) be completed.


Answer:
The contractor carrying out the works at Cairnshill Park & Ride has confirmed that installation of the bollards will commence during the week of 17 February 2025 with completion within 2 to 3 weeks.
The second phase, the installation of the barriers, will commence as soon as possible afterwards.