AQW 22513/22-27 Ms Kate Nicholl Alliance Party South Belfast
Tabled Date: 13/02/2025 Answered On Date: 19/02/2025 Priority Written: Yes
Question: To ask the Minister for Infrastructure to detail when the improvement works at Cairnshill park and ride facility will (i) begin; and (ii) be completed.
Answer:
The contractor carrying out the works at Cairnshill Park & Ride has confirmed that installation of the bollards will commence during the week of 17 February 2025 with completion within 2 to 3 weeks. The second phase, the installation of the barriers, will commence as soon as possible afterwards.
|