AQW 22782/22-27


Miss Órlaithí Flynn
Sinn Féin
West Belfast


Tabled Date: 18/02/2025
Answered On Date: 07/03/2025
Priority Written: No


Question:
To ask the Minister of Health (i) when the new Maternity Hospital at the Royal Victoria Hospital will open; and (ii) when construction work will commence on the new Children's Hospital at the Royal Victoria Hospital.


Answer:
(i) Belfast Health and Social Care Trust are not yet in a position to confirm when the new Maternity Hospital will open.  As previously reported to the Health Committee, the Trust are currently sampling the existing water system. Upon receipt of these sampling results the Trust will be able to determine the level of remediation works required to the water systems.  Once this remediation decision has been made, during April 2025, the Trust will be able to provide a programme for the opening of the new maternity hospital.
(ii) Construction work commenced on the new Children's Hospital on 3 March 2025.