AQW 28514/22-27


Mr Stephen Dunne
Democratic Unionist Party
North Down


Tabled Date: 10/06/2025
Answered On Date: 24/06/2025
Priority Written: No


Question:
To ask the Minister for Infrastructure to detail any projects from the Living With Water Programme being progressed during the 2025-26 financial year.


Answer:
My Department’s review of the affordability of the Living With Water in Belfast Plan concluded that the original 12-year delivery timescale was no longer achievable. Delivery of the projects in the Belfast Plan are now being taken forward by NI Water and my Department as normal business, at a pace and scale achievable within allocated budgets rather than through a formal programme.
Projects in the Belfast Plan being progressed by NI Water during the 2025-26 financial year include:
a £7m Upper Falls Storm Storage Project in West Belfast which will provide capacity to facilitate the connection of 1,200 homes;
a £0.9m project at Park Manor in Mallusk, that will resolve two Unsatisfactory Intermittent Discharges (UIDs) and will release capacity in the sewer network for 450 housing units;
a £0.5m project at Shore Road, Whiteabbey to resolve one UID and remove 1.3 hectares of impermeable area that is currently draining into its network;
work in the Carrickfergus, Greenisland and Seahill catchments to reduce spills to Belfast Lough from sewerage infrastructure; and
continued development of the Catchment Delivery Plan for the drainage area that is served by the Whitehouse Wastewater Treatment Works to inform future investments for NI Water as part of the PC21 and PC28 periods.
During 2025-26, my Department is also taking forward a flood alleviation feasibility study along the Knock and Loop rivers in south and east Belfast. As part of this feasibility study, my officials are working in partnership with the National Trust to take forward a Natural Flood Management pilot scheme in its Cregagh Glen property.