To ask the Minister of Health (i) to outline (a) the current timeline; and (b) projected costs for the development of the new health hub at the Fort George site, Derry; and (ii) what steps are being taken to ensure the project is not subject to further delays beyond the reported 2028-2031 timeframe.


Answer:
Construction of the Cityside health hub at the Fort George site remains contingent on business case approval and confirmation of affordability. Subject to these conditions, construction could begin on site in the Spring of 2028 with an on-programme completion of Summer 2031.
The current total project cost, excluding internal Department of Health costs is £141,691,439 based on the timeline above.