AQW 29263/22-27


Ms Connie Egan
Alliance Party
North Down


Tabled Date: 25/06/2025
Answered On Date: 30/06/2025
Priority Written: No


Question:
To ask the Minister of Education to detail an update on the timescale for a new building for Crawfordsburn Primary School.


Answer:
The contract for the construction of the new school building for Crawfordsburn Primary School was awarded to Bell Contracts Ltd on 14 May 2025.
Construction is due to commence on site in July 2025 with completion programmed for November 2026.