AQW 29594/22-27 Mr Robbie Butler Ulster Unionist Party Lagan Valley
Tabled Date: 01/07/2025 Answered On Date: 10/07/2025 Priority Written: No
Question: To ask the Minister for Infrastructure, in regard to the A1 Junctions Phase 2 scheme , whether all environmental and climate obligations have been signed-off and advanced by her Department, to ensure that these vital safety upgrades are delivered.
Answer:
The A5 judgement was extremely detailed, and it was the first legal test for the Climate Change Act and for Climate Action Plan – something every department will now have to deal with the outworkings of. We are working through the judgement, and it is too soon to conclude on its impact to wider infrastructure projects, including the A1 Junctions Phase 2 scheme.
|