AQW 29595/22-27


Mr Robbie Butler
Ulster Unionist Party
Lagan Valley


Tabled Date: 01/07/2025
Answered On Date: 10/07/2025
Priority Written: No


Question:
To ask the Minister for Infrastructure to detail when the works on the A1 Junctions Phase 2 scheme is anticipated to commence and complete.


Answer:
The current scheme programme for the A1 Junctions Phase 2 project anticipates commencement on site early Summer 2026 with a 3 year construction period, completing Summer 2029.