School Name | Scheme Detail | Current status |
Brookfield School | Additional accommodation, nursery unit | To complete March 2026 |
Brookfield School | Sept 26 accommodation | To complete August 2026 |
Carr Primary School, Lisburn | Replacement wastewater treatment plant | Tender returned 30/05/2025 |
Carr Primary School, Lisburn | Specialist Provision Accommodation | Awaiting direction from Children Young People Services (CYPS) |
Downshire Primary School, Hillsborough | Boundary Anomaly between School and Housing Development | Feasibility and Business Case (BC) assessment ongoing |
Dromore Central Primary School | Traffic Management Scheme /Carparking | To complete 25 August 2025 |
Dromore High School | Pupil toilets | To complete October 2025 |
Fair Hill Primary School, Dromara | Specialist Provision Accommodation Phase 1 | Start on site 16 June 2025 |
Fair Hill Primary School, Dromara | Specialist Provision Accommodation Phase 2 | Extent of works to be confirmed |
Knockmore Primary School, Lisburn | Traffic Management Scheme /Carparking | Feasibility and Business Case assessment ongoing |
Laurelhill Community College, Lisburn | Lobby security | To complete Feb 2026 |
Laurelhill Community College, Lisburn | Two additional modular classrooms | Business Case approved June 2025 |
Lisburn Central Primary School | Boundary & Fencing issue | Feasibility and business case assessment ongoing |
Lisburn Central Primary School | Security/Safeguarding works | Business case approved 27 June 2025 |
Lisburn Central Primary School | Specialist Provision Accommodation | Awaiting direction for 2026 provision |
Lisnagarvey High School, Lisburn | Three classroom modular accommodation | Completed 27/05/2025 |
Lisnagarvey High School, Lisburn | Additional changing facilities | Completed 02/04/2025 |
Lisnagarvey High School, Lisburn | Accessibility amendments - pupil specific | Site visit held end of May. Feasibility ongoing. |
Parkview School | Urgent additional accommodation | Awaiting Business Case approval |
Parkview School | Mapping exercise | Feasibility and business case assessment ongoing |
Parkview School | Refurb of hydrotherapy pool | Feasibility underway |
Parkview School | Specialist Accommodation | Feasibility to be completed |
Riverdale Primary School | Specialist Provision Accommodation | Awaiting direction for an estimated 2026 delivery |
St Aloysius’ Primary School, Lisburn | Standalone nursery unit | Business case approved. Design Team has been appointed |
St Mary's Primary School, Derrymore | Urgent health and safety fencing | Scheme completed 20/05/2025 |
St Michael’s Primary School, Finnis | Pupil Specific DDA Scheme - Visual Impairment | Works programmed to be completed by September 2025. |
St Patrick's Academy, Lisburn | Foyer Security | Business Case approved however discussions ongoing in relation to scheme design |
Tonagh Primary School, Lisburn | Specialist Provision Accommodation | Awaiting direction for an estimated 2026 delivery |